Installation of the ECO series cable access tiles is quick, easy and cost-effective. Following is the basic procedure for a typical floor plan.

 
  1. Select two longest right-angle walls as starting lines for first rows full size UniPanel.
  2. First step, apply Sound Attenuation Blanket.
  3. Then, plan the first piece UniPanel at the right-angle or recess to measure the 2 starting lines as shown in the drawing below. Connect first row UniPanel by half-size Base Connector along the starting walls. Allow 2 mm clearance between UniPanel and wall in order to avoid squeeze due to deviation of the wall.
  4. Continuous connection of UniPanel by Base Connector is simple. Steel Trench Cap may be installed before or after routing of cables.
  5. Ramps and perimeters installation plan also shown below:
 

 